Electricity supply system

Khu công nghiệp Nhơn Hội - Khu A - Điểm đến lý tưởng cho nhà đầu tư Hotline: 0256 3822427 - 0905 677 990

Electricity supply system

- Nhon Hoi Industrial Park - Park A is supplied with electricity from the national grid via a 220KV line from Phu Tai to a 220/110KV substation with a capacity of 2×125 MVA in Nhon Hoi EZ.

- The 110 KV line from 220/110KV station to 110/22KV substation with capacity of 2×63 MVA located in the industrial park.

- Transformer station will be installed in the factory in accordance with investor’s need by PC Binh Dinh.

- The investor signs a direct contract with Binh Dinh Power Company to install a power supply transformer station.

- Electricity prices according to regulations of the Ministry of Industry and Trade.

The power supply process is carried out according to the diagram below: