Land use planning of Nhon Hoi Industrial Park - Park A
File PDF: QH SDD KCNA 20-4-2022-HATCH
Total area of Nhon Hoi Industrial Park - Park A: 630 ha
Area of land for sublease according to the approved planning: 394 ha
Land area converted from industrial zone land to urban area: 236 ha
+ Land for construction of factories and enterprises:
A | Land for construction of factories and enterprises | 255,71 | |
1 | Producing pharmacology, medical materials…. | A3 | 31,66 |
– | A4 | 30,85 | |
– | A5 | 22,46 | |
2 | Processing wood and forest products | B1 | 30,46 |
– | B2 | 28,35 | |
– | B3 | 25,18 | |
3 | Processing of Seafood | B4 | 28,81 |
4 | Producing building materials | B5 | 27,81 |
– | B6 | 30,13 |
+ Land for construction of public and administrative service works
B | Service works - management - administration | 47,36 | |
1 | Land for administration works - services | CC1 | 6,94 |
– | CC2 | 7,47 | |
– | CC3 | 6,84 | |
– | A1 | 13,33 | |
– | A2 | 2,74 |
+ Land for construction of ecological green trees and flower gardens in the Industrial Park
C | Eco-green trees, flower gardens in Industrial Park | 41,88 | |
1 | Eco-green trees | S1 | 9,43 |
2 | Eco-green trees, flower gardens in Industrial Park | CX1, CX2, CX3 | 20,17 |
3 | Landscape greenery (D1, D2, D3, N2, N4) | 12,28 |
+ Area of land for traffic (IP: 35.06 ha; Urban: 18.1 ha): 53.16 ha.
+ Parking area P1 (1.32ha), P2 (0.68ha)
+ Land area for key technical infrastructure works
F | Technical infrastructure focal works | 4,03 | |
1 | Transformer station 110/22 KV | K2 | 0,74 |
2 | Solid waste concentration ground | K4 | 0,89 |
3 | Internal water supply station | CCN | 0,27 |
4 | Water drainage | KTN | 2,13 |
+ Minimum leased land area: Land for construction of factories, enterprises, public and administrative services: at least 10,000 m2.
Construction regulations in Nhon Hoi Industrial Park - Park A
- Building density and high floors:
+ For land for construction of enterprises and factories: 60% and from 1 to 3 floors or higher depending on the technology line.
+ For land for construction of public and administrative services: 35% and from 5 to 9 floors.
- Construction setback:
+ For the main road of the economic zone, the specialized road to the west, the road with cross section>=29m: 7m.
+ For roads with cross section <=27m: 5m.
- Roadside fence:
Built according to the design model promulgated together with Decision No. 1481/QD-BQL dated November 7, 2007 of Nhon Hoi Management Economic Zone.